Sprints
Sprint spotlights for the Electronics area, generated every week from the project board and reviewed by the area PM before merging. Newest sprint first.
Status legend:
- 💻 Development
- 🔍 Research
- 📝 Documentation
- 🔧 Bug fixing
Sprint 3 · 2026-09-21 → 2026-10-11
Sprint plan
2 tasks planned for this sprint.
In Progress:
- Becca-731, LARC 💻 Solder and test gripper PCB (P1, #1203)
Todo:
- Jasiel Aldana Palacios 💻 Update electronics diagram for FRIDA (P2, #1319)
Week 1 · 2026-09-21 → 2026-10-02
In Progress:
- Becca-731, LARC 💻 Solder and test gripper PCB (P1, #1203)
Not started: 1 task.
Sprint 2 · 2026-08-31 → 2026-09-20
Sprint plan
2 tasks planned for this sprint.
Todo:
- Becca-731, LARC 💻 Solder and test gripper PCB (P1, #1203)
- Unassigned 💻 Determine FRIDA's peak amperage requirement (#1250)
Week 1 · 2026-08-31 → 2026-09-06
Not started: 2 tasks.
Sprint results
1/3 tasks done (33%).
This sprint focused on the Electronics area tasks. The team successfully added the extra 12V power cable for the hub. Meanwhile, soldering and testing the gripper PCB and determining FRIDA's peak amperage requirement remain pending.
Done:
- Jasiel Aldana Palacios 💻 Add extra 12V power cable for hub (P1, #1276)
Carried over:
- Becca-731, LARC 💻 Solder and test gripper PCB (In Progress, P1, moved to Sprint 3, #1203)
- Becca-731 💻 Determine FRIDA's peak amperage requirement (Todo, no longer in a sprint, #1250)
Sprint 1 · 2026-08-10 → 2026-08-30
Sprint results
2/2 tasks done (100%) · P0: 2/2.
Done: